title
An ordinance authorizing The Metropolitan Government of Nashville and Davidson County to abandon existing public water and sanitary sewer mains, sanitary sewer manholes and easements, and to accept new public sanitary sewer main, sanitary sewer manhole and easements, for six properties located at Victory Avenue, South 1st Street, Shelby Avenue, Woodland Street, Titans Way, and Russell Street, also known as the Nissan Stadium Infrastructure Project (MWS Project Nos. 23-WL-27 and 23-SL-52 and Proposal No. 2023M-082ES-001).
body
WHEREAS, the abandonment of approximately 1,993 linear feet of existing 12-inch water main (DIP), approximately 251 linear feet of existing eight-inch sanitary sewer main (PVC), approximately 222 linear feet of existing 18-inch sanitary sewer main (PVC), four sanitary sewer manholes and easements, and the acceptance of approximately 108 linear feet of new eight-inch sanitary sewer main (PVC), one new sanitary sewer manhole and easements, for six properties located at Victory Avenue, South 1st Street, Shelby Avenue, Woodland Street, Titans Way, and Russell Street, also known as the Nissan Stadium Infrastructure Project, are needed to construct project numbers 23-WL-27 and 23-SL-52; and,
WHEREAS, the Metropolitan Planning Commission approved mandatory referral No. 2023M-082ES-001 on May 31, 2023, for the abandonment and acceptance of said water and sewer mains, sanitary sewer manholes, and easements.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY:
Section 1. The Metropolitan Government of Nashville and Davidson County is authorized to abandon approximately 1,993 linear feet of existing 12-inch water main (DIP), approximately 251 linear feet of existing eight-inch sanitary sewer main (PVC), approximately 222 linear feet of existing 18-inch sanitary sewer main (PVC), four sanitary sewer manholes and easements, and to accept approximately 108 linear feet of new eight-inch sanitary sewer main (PVC), one new sanitary sewer manhole and easements, for six properties located at Victory Avenue, South 1st Street, Shelby Avenue, Woodland Street, Titans Way, and Russell Street, also known as the Nissan Stadium Infrastructure Project, as shown on Exhibits 1 and 2, which are attached hereto and incorporated by reference.
Section 2. The Directors of Water and Sewerage Services and Public Property Administration are authorized to execute such documents as may be necessary and appropriate to carry out the abandonment and acceptance authorized by this ordinance.
Section 3. Amendments to this legislation shall be approved by resolution.
Section 4. This ordinance shall take effect from and after its final passage, the welfare of The Metropolitan Government of Nashville and Davidson County requiring it.
Agenda Analysis
Analysis
This ordinance abandons approximately 1,993 linear feet of existing 12-inch water main (DIP), approximately 251 linear feet of existing eight-inch sanitary sewer main (PVC), approximately 222 linear feet of existing 18-inch sanitary sewer main (PVC), four sanitary sewer manholes and easements, and accepts approximately 108 linear feet of new eight-inch sanitary sewer main (PVC), one new sanitary sewer manhole and easements for six properties located at Victory Avenue, South 1st Street, Shelby Avenue, Woodland Street, Titans Way, and Russell Street, also known as the Nissan Stadium Infrastructure Project.
Future amendments to this legislation may be approved by resolution. This ordinance has been approved by the Planning Commission.
Fiscal Note: This ordinance has no cost to Metro. Abandoned and donated easements have no market value according to the Department of Water Services.