Title: A resolution authorizing The Metropolitan Government of Nashville and Davidson County to abandon existing public water and sanitary sewer mains, fire hydrant assembly and sanitary sewer manholes, and to accept new public water and sanitary sewer mains, fire hydrant assembly and sanitary sewer manholes, for property located at 110 Berry Street, also known as Berry Street Infrastructure (MWS Project Nos. 25-WL-71 and 25-SL-167 and Proposal No. 2025M-197ES-001).
Sponsors: Sean Parker, Rollin Horton, Quin Evans-Segall
Attachments: 1. Exhibit 1, 2. PC Approval Letter
title
A resolution authorizing The Metropolitan Government of Nashville and Davidson County to abandon existing public water and sanitary sewer mains, fire hydrant assembly and sanitary sewer manholes, and to accept new public water and sanitary sewer mains, fire hydrant assembly and sanitary sewer manholes, for property located at 110 Berry Street, also known as Berry Street Infrastructure (MWS Project Nos. 25-WL-71 and 25-SL-167 and Proposal No. 2025M-197ES-001).
body
WHEREAS, the abandonment of approximately 50 linear feet of existing six-inch water main, approximately 363 linear feet of existing 12-inch water main, approximately 170 linear feet of existing 12-inch sanitary sewer main, approximately 397 linear feet of existing 15-inch sanitary sewer main, one fire hydrant assembly and two sanitary sewer manholes, and the acceptance of approximately 57 linear feet of new eight-inch water main (DIP), approximately 365 linear feet of new 12-inch water main (DIP), approximately 63 linear feet of new 12-inch sanitary sewer main (PVC), approximately 260 linear feet of new 15-inch sanitary sewer main (PVC), approximately 167 linear feet of new 15-inch sanitary sewer main (DIP), one new fire hydrant assembly and five new sanitary sewer manholes, for property located at 110 Berry Street, also known as Berry Street Infrastructure, are needed to construct project numbers 25-WL-71 and 25-SL-167; and,
WHEREAS, BL2024-345 authorizes the Metropolitan Department of Water and Sewerage Services to approve extensions, additions, improvement, or works by resolution of the Metropolitan Council; and,
WHEREAS, the Metropolitan Planning Commission approved with conditions mandatory referral No. 2025M-197ES-001 on January 28, 2026, for the abandonment and acceptance of said water and sanitary sewer mains, fire hydrant assemblies, and sanitary sewer manholes; and,
WHEREAS, NES's condition that all work must maintain clearances with any utility poles to prevent undermining the integrit...