File #: RS2026-2207   
Type: Resolution Status: Resolution
File created: 8/6/2026 In control: Planning Commission
On agenda: 8/18/2026 Final action:
Title: A resolution approving Amendment Number 6 to an intergovernmental agreement by and between the Tennessee Department of Transportation ("TDOT") and the Metropolitan Government, by and through the Nashville Department of Transportation and Multimodal Infrastructure ("NDOT"), for improvements on Jefferson Street, Federal No. STP-M-1900(28), State No. 19LPLM-F3-011, PIN 103490.00, Prop No. (2026M-044AG-001).
Sponsors: Brandon Taylor, Kyonzte Toombs, Rollin Horton, Quin Evans-Segall, Brenda Gadd
Attachments: 1. Exhibit
title
A resolution approving Amendment Number 6 to an intergovernmental agreement by and between the Tennessee Department of Transportation ("TDOT") and the Metropolitan Government, by and through the Nashville Department of Transportation and Multimodal Infrastructure ("NDOT"), for improvements on Jefferson Street, Federal No. STP-M-1900(28), State No. 19LPLM-F3-011, PIN 103490.00, Prop No. (2026M-044AG-001).
body
WHEREAS, RS2008-245 approved an intergovernmental agreement between TDOT and the Metropolitan Government, by and through the Metropolitan Public Works Department, now known as NDOT ("Metro"), for improvements on Jefferson Street; and,
WHEREAS, based upon the Agreement, TDOT awarded to Metro a grant in an amount not to exceed $920,808.00, with a required match of $480,203.00 by the Metropolitan Government, for intersection improvements on Jefferson Street; and,
WHEREAS, RS2013-745 approved Amendment Number 1 to the Agreement, which extended the original project completion date to June 1, 2017, and specifically identified the two intersections on Jefferson Street which are to be improved, 28th Avenue/Ed Temple and 21st Avenue North; and,
WHEREAS, RS2017-708 approved Amendment Number 2 to the Agreement, which extended the project completion date to June 1, 2019, in light of a traffic study that made additional recommendations that affected the project schedule; and,
WHEREAS, RS2019-1624 approved Amendment Number 3 to the Agreement, which extended the project completion date to December 31, 2020, in light of a revised schedule for delivery of final construction plans; and,
WHEREAS, RS2020-649 approved Amendment Number 4 to the Agreement, which extended the project completion date to December 31, 2022, to allow time to procure right-of-way and construction inspection on-call services from TDOT, and approved the TDOT-awarded grant to an amount not to exceed $2,880,000, with an increased required match of $1,045,563 from Metro, to cover the design, right-of...