title
An ordinance authorizing The Metropolitan Government of Nashville and Davidson County to abandon existing public water and sanitary sewer mains, fire hydrant assemblies, sanitary sewer manholes and easements, and to accept new public water and sanitary sewer mains, fire hydrant assemblies, sanitary sewer manholes and easements, for 17 properties located at Cowan Street, Waterside Drive, River North Boulevard and North 9th Street, also known as River North Early Works (MWS Project Nos. 25-WL-73 & 25-SL-170 and Proposal No. 2026M-005ES-001).
body
WHEREAS, the abandonment of approximately 1,011 linear feet of existing eight-inch water main, approximately 2,600 linear feet of existing 12-inch water main, approximately 2,728 linear feet of existing eight-inch sanitary sewer main, approximately 504 linear feet of existing 12-inch sanitary sewer main, approximately 1,341 linear feet of existing 15-inch sanitary sewer main, approximately 137 linear feet of 30-inch sanitary sewer main with TDEC approval, 11 fire hydrant assemblies, 22 sanitary sewer manholes and easements, and the acceptance of approximately 920 linear feet of new 12-inch water main (DIP), approximately 817 linear feet of new 12-inch sanitary sewer main (DIP), approximately 626 linear feet of new 30-inch sanitary sewer main (DIP), four fire hydrant assemblies, nine sanitary sewer manholes and easements, for 17 properties located at Cowan Street, Waterside Drive, River North Boulevard and North 9th Street, also known as River North Early Works, are needed to construct Project Nos. 25-WL-73 and 25-SL-170; and,
WHEREAS, the Metropolitan Planning Commission approved mandatory referral No. 2026M-005ES-001 on February 19, 2026, for the abandonment and acceptance of said water and sanitary sewer mains, fire hydrant assemblies, sanitary sewer manholes and associated easements.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY:
Section 1. The Metropolitan Government of Nashville and Davidson County is authorized to abandon approximately 1,011 linear feet of existing eight-inch water main, approximately 2,600 linear feet of existing 12-inch water main, approximately 2,728 linear feet of existing eight-inch sanitary sewer main, approximately 504 linear feet of existing 12-inch sanitary sewer main, approximately 1,341 linear feet of existing 15-inch sanitary sewer main, approximately 137 linear feet of 30-inch sanitary sewer main with TDEC approval, 11 fire hydrant assemblies, 22 sanitary sewer manholes and easements, and to accept approximately 920 linear feet of new 12-inch water main (DIP), approximately 817 linear feet of new 12-inch sanitary sewer main (DIP), approximately 626 linear feet of new 30-inch sanitary sewer main (DIP), four fire hydrant assemblies, nine sanitary sewer manholes and easements, for 17 properties located at Cowan Street, Waterside Drive, River North Boulevard and North 9th Street, also known as River North Early Works, as shown on Exhibit 1 and 2 which are attached hereto and incorporated by reference.
Section 2. The Directors of Water and Sewerage Services and Public Property Administration are authorized to execute such documents as may be necessary and appropriate to carry out the abandonment and acceptance authorized by this ordinance.
Section 3. Amendments to this legislation shall be approved by resolution.
Section 4. This ordinance shall take effect from and after its final passage, the welfare of The Metropolitan Government of Nashville and Davidson County requiring it.