Legislation Details

File #: BL2026-1665   
Type: Bill Status: First Reading
File created: 11/20/2026 In control: Planning Commission
On agenda: 12/1/2026 Final action:
Title: An ordinance amending Title 17 of the Metropolitan Code of Laws regarding decommissioning of unused industrial facilities (Proposal No. 2026Z-018TX-001).
Sponsors: Mike Cortese
title
An ordinance amending Title 17 of the Metropolitan Code of Laws regarding decommissioning of unused industrial facilities (Proposal No. 2026Z-018TX-001).
body
BE IT ENACTED BY THE COUNCIL OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY:
Section 1. That Section 17.04.060 of the Metropolitan Code is hereby amended by adding the following new definitions in alphabetical order:
“Decommissioning” means the removal and restoration of a property and includes the removal of all hazardous materials and contents, including cabling, electrical components, cooling systems, any contaminated soils, any electrical generators, and other associated facilities, as well as the regrading of any earth disturbed during removal. Decommissioning shall not require the removal of warehouses or facilities without a specialized usage.
“Decommissioning Cost” means the estimate cost of decommissioning a property, less the net salvage value of the equipment as determined by an independent certified Professional Engineer licensed in the State of Tennessee.
Section 2. That Chapter 17.28 of the Metropolitan Code of Laws is hereby amended by adding the following as a new section 17.28.090
17.28.090 – Decommissioning
A. Applicability.
These standards shall apply to any application for the following uses:
1. Data center – large
2. Data center – medium
3. Data center – small
In the event of sale or transfer of the facility, the acquiring party shall adhere to the original monetary and operational decommissioning requirements set forth for the original developer.
B. Decommissioning Plan.
1. Prior to approval of any applicable permit, the applicant shall submit a decommissioning plan for approval by the zoning administrator.
2. The decommissioning plan shall include:
a. The anticipated life of the industrial facility; and
b. the decommissioning cost; and
c. a timeline for completion of decommissioning; and
d. a detailed scope of work for the decommissioning.
C. Financial As...